Tag Archives: building information modeling

The State of IPD and BIM: an Owner’s Perspective


Since owners benefit as much – if not more – than contractors and architects from use of the new digital technology tools and collaborative work processes now used on many building projects, why is it that we so seldom hear about building information modeling (BIM) and integrated project delivery (IPD) from the owner’s side?

To help rectify this situation, I decided to conduct an interview with Symphony Partners.

Clay Goser and Dawn Naney served as owners at BJC HealthCare prior to starting Symphony LLC and are extremely knowledgeable about how these new tools and processes serve the entire project team.

Saying you can do IPD without regard for a contract is a recipe for disaster: True or False?

Clay: False. It’s not about a contract –

Dawn: –  it’s about getting people to behave differently.

Clay: A contract is a tool that has two purposes – to set business terms and conditions and to allow the team  to have the critical conversations around expectations.  The reason IFOA agreements often work is that they are different enough that they introduce risk and firms want to know what that means for them.  The Integrated Form of Agreement (IFoA) begins to define how a group works as an organization.  What we don’t have most of the time is a conversation about what we’re going to do and how we are going to do it. The nature of IPD is getting people to come back together – collaborating to a greater extent. Collaboration is the behavior.

Dawn: The contract has a different purpose. The purpose of IPD is to identify and proactively manage risk and capitalize on opportunity within the delivery process.  The purpose of the contract is different. It asks: what are you going to do, how much are you going to get paid to do it and the process outputs required (i.e. status reports, schedules, RFI turn around times etc.) and does not address how are you are going to operate as a team and the procedures to implement the project.   Defining what you are going to build and HOW you are going to build it is critical to successful integration outside of the IFoA contract.  This is the behavior change.

What do you see as the current state of IPD?Clay: IPD is firmly in Gartner’s Hype Cycle©  as we try to define what IPD will do for us. We will head for the Trough of  Disillusionment© -[ meaning when inflated expectations are not met, there will be a threat of abandonment. All new technologies and ideas go through this cycle.  Some survive, some don’t and that is dependent upon how long and how deep the trough lasts.   The risk we introduce is that as firms start to market IPD and implement without completely understanding why it works those waiting for IPD to become mainstream before introducing this new delivery method to their organizations, will abandon the concept as unpredictable and risky and start to question the value of integration.

Dawn: One challenge we’re having as an industry is distinguishing what is – and is not – an IPD project. We need to change the question.

Whether an IPD project is pure or IPD-ish is not the right question?

Dawn: Right.  There isn’t a standard checklist of “do this” that makes a team “IPD”.

Clay: Here’s an example: some teams feel that you have to  do BIM throughout the entire project to be IPD.   However, a team, for example, that adopts BIM to answer key critical questions that the team deems important to their success without creating waste – such as using BIM to define how the exterior structure ties into an existing structure that’s ‘pure’ IPD or integration at it’s best.   I have seen many design teams implement 100% BIM only to have the trade contractors turn around and dismiss the model because the model isn’t useful to fabricate from. True IPD would define how much BIM is needed from the design team to facilitate understanding and fabrication by the trades, stop there and let the person best equipped to carry it forward, carry it forward.   It’s based on the project, time and circumstance.

What do you see as the impact of the economy on IPD?

Dawn: When an owner goes for the lowest bid, they often just get what they pay for not what they need, which results in change.   We incent bad behavior when we, as Owners, award solely on lowest bid…i.e. we incent firms to hide the risk and submit change orders to course correct the scope instead of buying intelligent performance to avoid the risks and do it right the first time and eliminating the waste. Owners are under the impression that we’re in a buyer’s market, so they’re holding back from pursuing IPD. The market needs to look for better, smarter ways to be profitable and sustainable in a down economy and Owners needs to look for better, smarter ways to conserve precious capital.   Buying through low bid introduces risk to both parties.

Clay: As a percentage, all construction projects vs. IPD projects, the number of IPD projects is very small. There are a lot of conversations about how prevalent IPD is now. The industry is ramping up. Every IPD project is a petri dish from which we continue to learn. We’re at a very early adoption stage of IPD.

The economy is driving us to work and behave differently: smarter.

When people say “once the economy comes back we’ll consider change:” IPD won’t go gangbusters. When firms are busy they don’t have time to think about how to work better, more effectively: they are worried about how to get the work done.  People should be thinking about how to work more effectively NOW, so that they can differentiate themselves when the economy gains momentum.

What has been the impact of IPD case studies – those published by the AIA and University of  Minnesota? Is it your impression that owners are reading them?

Clay: Owners are interested in the IPD case studies, especially owners of robust and innovative organizations dedicated to continuous learning. Owners focused on keeping their head above water or adverse to risk aren’t as interested in the IPD case studies.

Owner-involvement in IPD is critical to a project’s success: Is owner-led IPD the only way to go?

Clay: Owners impact vendors – architects, engineers and contractors – by incentivizing and setting specifications, and not always in a good way. As for IPD, owners don’t always understand what IPD means.  Do Design-Bid-Build jobs go poorly? Yes. Do Design-Bid-Build jobs go well? Yes. What’s the difference? The team – how they cooperate, how they behave.

The question needs to be: How do we produce good collaboration and reproduce it?

Dawn: Owners must ask and seek out why IPD worked when it does work for them. Most of the time, it’s because the team wanted it to work well. The relationships were better and they problem solved in the best interest of the project, not themselves. Team formation is critical to successful integration.  Each new project is a melting-pot of different cultures melding together.    When you bring the right people to the table at the right time to best inform project decisions this integration occurs earlier in the process allowing for the critical forming, norming, storming and performing of the team to occur prior to construction when the cost of change escalates exponentially. IPD allows for time at the beginning for the team to create a team culture and define how they are going to work together.

Clay: When you show up early in the design process, IPD allows you to have a conversation about how you’re going to work vs. just show-up and perform.  Many firms are marketing IPD to Owners promoting the need for an IFoA agreement.  Many Owners don’t know what’s in the contract. What it involves or how it effects all of the team members as a group.

Architects, engineers and contractors say we have to do something different from Design-Bid-Build to remain profitable. Owners say: why don’t architects, engineers and contractors drive IPD?

Keep in mind, IPD after all, when it was first created, was used by the team without knowledge by the Owner!

Dawn:  Owners are asking: If IPD is so great, why haven’t you been doing it for 100 years?  Why do I need to incentivize you to “collaborate” by removing risk?

Owners are used to accepting the lowest bid. They have a hard time swallowing the IPD pill because it isn’t quantifiable or defendable to their Boards and Investors.

We need to educate Owners that IPD allows you to solve problems, avoiding risk and uncovering opportunities we didn’t know existed.   A lot of the time teams don’t know what the real problems are so they solve symptoms. What they need to do – and this comes from Lean – is identify the root problem and solve it.  We need to understand the cause and effect relationships of our behavior.

Clay:  An owner empowers an IPD team but doesn’t need to demand it.

Dawn: IPD is a smart way to work. If you don’t have the owner driving IPD, integrate anyway and reap the benefits as a best business practice.   It makes the team members more profitable, reduces risk and informs an improvement strategy that is sustainable and lucrative for future business.

Can you do IPD without BIM?

Clay: You can’t divorce Lean from BIM from IPD. Lean is a not a methodology, but a philosophy.  BIM is a tool.   You don’t have to do BIM to be IPD. IPD is a means to an end. Lean is the end. BIM is a way to get there.   You can do IPD without BIM and have great results. BIM is a tool that helps facilitate communication – understanding what it is you are trying to achieve.

Likewise, you can use BIM without IPD but the benefits may be marginalized. BIM and IPD coupled together are stronger.

Rate obstacles in terms of most prevalent to least: owner involvement (thru ambivalence, skepticism, indifference); insurance issues; legal issues; blurring of roles; who owns the BIM; collaboration; need for education/processes; inflexible behavior; MEP/engineers; resistance to change.

Clay: The need for education and a consistent definition of what IPD really means, not how but what you are trying to accomplish is very important.

Dawn: Most often, people want to jump into IPD and make it a revolution – not an evolution. Most owners don’t have the flexibility to change to IPD right away. IPD requires a change in process and considerable amount of change adoption.

People don’t resist change – they resist risk.  Remove the risk, remove the resistance.

Clay:  The collaborative nature of a nimble-thinking team approaches obstacles as problems to be solved.

Integration is the “leaning” of the entire delivery process wherever people and process touch each other.

We need to reframe “obstacles” as just “problems to be solved.”

Clay Goser has been responsible for projects in nine hospitals and over a half billion in medical construction in and around the metropolitan St Louis area. He left BJC Healthcare to start Symphony LLC, a company consulting in strategic improvement in portfolio, program and project management. Read more about Clay here.

Dawn Naney has over 15 years of experience establishing and managing teams responsible for the successful planning and execution of portfolios, programs and projects in a variety of fields including design/construction, information technology, clinical interventions and process improvement, primarily in the healthcare industry. Prior to serving as consultant at Symphony LLC, Dawn served as an owner in the area of Portfolio/Program/Project Management for the Center for Clinical Excellence. Read more about Dawn here.

Symphony LLC is a consulting firm providing collaborative leadership, education and management of capital portfolios, programs and projects primarily for the design and construction industry. Symphony balances tradition and innovation to lead high performance teams focused on delivering the best value for a fair price. Best value for capital expended is derived from improvements resulting in better quality and performance, reduced cost and competitive differentiation for owners and service providers. Learn more about Symphony LLC here.

11 Comments

Filed under Uncategorized

Two Books to Transform the AEC Industry


This past week I had the opportunity to read two significant AEC industry books – one of which I had been meaning to read for several years, the other just having been published.

Building Information Modeling (BIM) and Integrated Project Delivery (IPD) are central to each of these books, whereas they were relegated to a single chapter in Barry LePatner’s otherwise excellent book, Broken Buildings, Busted Budgets: How to Fix America’s Trillion-Dollar Construction Industry.

I’ll start with The Commercial Real Estate Revolution: Nine Transforming Keys to Lowering Costs, Cutting Waste, and Driving Change in a Broken Industry, by Rex Miller et al, a quartet of construction industry professionals.

The Commercial Real Estate Revolution

I didn’t read this book when it first came out (July 2009) for one reason and one reason alone: it cost $40.

And for a second reason: I was writing my own AEC industry book ($75!) and didn’t want to be influenced by its findings.

And a third: I found a few words in the title (Commercial Real Estate + Revolution) off-putting. Sounded more 2006 than 2009.

And a fourth (I’ll get to that in a moment.)

Looking back, I should have ignored these reasons and read the book when the ink was still wet.Observations

The foreword by Metropolis Magazine’s Susan S. Szenasy alone is worth the price of the book  $39.95  ($12 used)

The book grew out of a wide-ranging group of dedicated industry players called The Mindshift consortium (the name was my fourth reason. It sounded vaguely un-construction-like.) That the consortium (not a think-tank but a “do-tank”) grew out of weekly discussions over pancakes (the Pancake Roundtable) at a local diner grounds the book in real people with real concerns.

This book has a big heart. It’s the kind of commercial real estate book that’s not afraid to quote Joseph Campbell on the power of metaphors to induce change.

Unlike LePatner, Miller and his cohorts are not only looking to fix what’s broken in the industry, but transform it. That alone distinguishes this book.

Read Chapter 2: What Every Executive Needs to Know About Low-Bid Contracting, and you’ll never use Design-Bid-Build as a delivery method again.

The Nine Keys

The second two-thirds of the book present The Nine Keys of Mindshift, including Four Principles, Four Tools, One Hidden Revolution

Key 1: Trust-Base Team Formation (Principle) – How you select your team, whom you select, and the process you use to form them into a team is the most important component of a succesful project.

Key 2: Early Collaboration (Principle) – Clear channels of communication and efficient ways of working together must be established to ensure ultimate success.

Key 3: Built-In Sustainability (Principle) – Sustainability becomes a natural result of better design and the elimination of waste.

Key 4: Transformational Leadership (Principle) – Leadership must be flexible, trusting team members to work together and empowering them to solve problems.

Key 5: Big “BIM” (Tool) – Building Information Modeling is a game-changing technology. It facilitates early collaboration and allows the team to rehearse and resolve issues in a virtual environment that carries over seamlessly to real construction.

Key 6: Integrated Project Delivery (Tool) – The “siloed” hierarchy of Design-Bid-Build becomes a round table in IPD as the planning, design, and implementation process integrate all team members’ input and participation. Lean Construction is an increasingly important tool for team members to identify waste and measure performance.

Key 7: Trust-Based Agreements and Client-Centered Incentives (Tool) – All team members assume an equal degree of shared risk and reward, and profitability is inextricably linked to the success of the project.

Key 8: Offsite Manufacturing (Tool) – Fabricating materials offsite and in advance provides an opportunity to change the nature, quality and future of construction.

Key 9: Workplace Productivity (The Hidden Revolution) – When buildings are uniquely designed and constructed with the end-user in mind, the space created can enhance the quality of life and work for those using it and will deliver higher value to the owner. Alternative workplace solutions are one example of the mindshift model that stresses long-term strategic value over short-term transactional returns.

The authors write: “Building, at its essence, is a relational practice. It is creative. And, when done well, it is restorative.” I believe, if you haven’t already done so, that reading this book will be an equally restorative experience for you.

You can find a good summary and background here http://www.haworth.com/en-us/Knowledge/Mindshift/Pages/The-Consortium.aspx

An article providing some background by the author in DesignIntelligence here

And read chapter 1 (“The $500 Billion Black Hole”) here http://media.wiley.com/product_data/excerpt/65/04704574/0470457465.pdf

Makers of the Environment

Don’t be alarmed if you haven’t heard of this book.

Makers of the Environment: Building Resilience Into Our World, One Model at a Time, by BIG BIM little bim author, Finith E. Jernigan was released December 15, 2011 ($9.99 Kindle, though you will want a hard copy of the book so you can scan the QR code-like tags. I’ll get top those in a moment.)

Billed as “the first information model in a book” (where BIM = book information model,) Makers of the Environment is a true 3D reading experience.

You can read the book straight through or, using Microsoft TAGs spread throughout the book, link to the book’s website for richer data, videos, related articles and a deeper look into the subject at hand.

You can imagine my surprise while scanning one of the codes to find it lead to one of my own blog posts (i.e. a surreal experience.)

Read more about it here. Observations

The book presents straightforward short chapters on various topics. These are followed by scenario plans that take place in the near future – or the recent past – and are populated by characters devised by the author. Here’s how it is described:

Makers of the Environment shows how an organization in a small, depressed rural county can pull together to take advantage of the opportunities to become a world leader in the management of information to change our world. With systems and processes such as Makers describes, we for the first time in history can define and manage real-world assets. The book’s central design future forms the backbone for three scenarios show how to use the information to improve the world.

Three of these scenarios are presented in the prologue, even before you hit the first chapter (which opens with another scenario.) It’s admittedly a bit rough-going, but well-worth the journey when you arrive at the expository writing and tags. That’s when the book really transforms (some, such as the tag on Georeferencing, are spectacular.)

The book presents a world of making or makers that is wholly inclusive and democratic. The book presents an industry where laypeople – real people – are participants who engage creatively and productively in the making and preservation of their world, and in doing so receive value directly from their involvement.

Technology is leveling the field for everyone. No longer must we rely on experts talking at us as we find solutions to today’s most vexing problems. We can all participate directly in the decisions, with real data, to get greater certainty of outcomes.

That said, one wonders if the title ought to have been Stewarts of the Environment or Makers of the Built Environment?

Some caveats: There is a great deal of repetition (whole sentences and even pages: p. 21-22, for example, are mysteriously repeated at length on p. 23-25) and the book, self-published, could have benefitted from some heavy editing and copyediting. Why, for example, are some chapters in grey background and others not? Some of the technology discussions come across as infomercials. Some of the scenarios sound as though they are taking place next week rather than in 10 years (this can be disconcerting for the reader who is constantly being asked by the text to place themselves in time.) The book’s sentences – that make up the paragraphs – don’t have a great deal of variation or differentiation in length. In this sense, the book sometimes feels as though it was in fact an information model in that it can feel as though it were written by a computer. This is a book that has enough valuable information to recreate the world – but, nonetheless, is still in search of a heart.

Kudos to the author for taking the innovative and creative route – it is always the more difficult to be a trailblazer.

It is very hard in a brief review to summarize what comes across as a comprehensive worldview – a view of the near-term future. Here’s how the book is described:

Makers of the Environment merges storytelling with everyday reality to offer a moment where we can rethink our expectations to understand how technology can and should be used to improve our world. The book makes the extraordinary ordinary, offering a vision on how society can take advantage of new and emerging technology to create a better, more sustainable world for our children.

I’ve barely touched on some of the major themes and ideas presented. You truly have to read the book for yourself to fully grasp it’s breadth, potential impact on your thinking and vision of the near-term future: the next steps for our industry and planet.

Forgiving some of the book’s more experimental and editorial shortcomings, I highly recommend Makers of the Environment for anyone and everyone working in – or around – the AECO industry.

6 Comments

Filed under BIM, business model, construction industry, Integrated Project Delivery, IPD, people

MoneyBIMball


With Moneyball in theaters, the playoff season in full swing, and the 2003 book by Michael Lewis climbing in standings, data geeks are all the rage.

This fact cannot be lost on architects and others in the construction industry.

In the movie and book, the 2002 Oakland Athletics overlook the former criteria for player selection (brawn, looks and stature) in favor of data and information.

Doing so was unorthodox to say the least. The equivalent of design professionals proceeding with a design based on data over visuals.

But in doing so, the Athletics managed an all-time record winning streak and made the playoffs with the major’s smallest budget.

Which leads us to ask of ourselves two questions:

  • Is it time we honor our inner geek?
  • Is it time we get creative with our data?

Information and Process Builders

In his brilliant undated letter to the profession entitled “BIM ball,” Kimon Onuma’s focus was not on the 3D nature of BIM, but almost entirely on the “I” of BIM:

“Information and data integrated with 3D” models.

Due to the threatening ‘evolve or dissolve’ resolve of the subtitle, this fact was lost on the average reader.

A few cogent lines from the letter tell the story:

  • We charge our clients 6% plus of construction costs to assemble information into documents
  • Most of the knowledge and information that is assembled for a project goes into the lines of a CAD file that essentially has only one use
  • The value in architectural services rests in the knowledge and experience to assemble information and execute projects
  • The only possible solution is to solve this using the technologies available in Building Information Modeling, standards and interoperability.
  • Architects are positioned at the center of the design and construction process not as the “master builder” integrating and organizing all the disparate pieces of the building but now as the information and process builders and coordinators in this process

From this we can deduce that information is at the heart of our evolution as a profession and industry.

Which leads us to ask:

What will we do with the information available to us?

To continue the base hits of visualization and clash detection or home runs of analysis?

Reevaluating Strategies that Produce Wins on the Field

Just as Moneyball 

  • focused on the general manager – our story ought to focus on the BIM manager
  • focused on the team’s modernized, analytical approach to assembling a competitive team – our focus ought to be on the BIM analytics
  • has done wonders for unorthodox analytics – our use of BIM ought to do the same for analysis
  • team used statistics that are relics of a 19th century view of the game – our industry continues to use methodologies for estimating cost and anticipating schedules and predicting accuracy that are relics of centuries past.
  • central premise is that the collected wisdom of baseball insiders (players, managers, coaches, scouts, front office) over the past century is subjective and often flawed – our focus ought to be on the fact that our own collective wisdom has not led to increased value or productivity nor reduced waste
  • isn’t really about baseball or statistics, but about challenging conventional wisdom with data – our understanding ought to be that BIM isn’t about technology, but rather challenging design and construction professionals to use information available to them to increase productivity and reduce waste.

Like the general manager in the movie, it’s time we give the data a long hard look.

Like the 2002 Oakland A’s, we as a profession and industry ought to be re-evaluating the strategies that produce wins on the field.

Anything but a Field of Dreams

There’s a fear that BIM does away with design in favor of data.

This of course couldn’t be further from the truth.

As long as architecture remains an art, it will always maintain the element of the will.

Architectural design is an essay in willfulness.

Design work that is described and then either justified (with information) or rationalized (with pedagogue and agendas.)

Or post-rationalize out in the field.

This last option – our industry’s history up until now – has been anything but a field of dreams.

In 1896, Louis Sullivan asserted:

Form Follows Function

In 2011 (and beyond) in order to reach home:

Firms Follow Information

6 Comments

Filed under analysis, BIM, BIM manager, BIM organizations, modeling, people, process

Is BIM in 10 Words or Less Still BIM?


Recently I was
asked to summarize my 240 page book in a single sentence.

It’s the sort of reductionist thinking that can lead to some less than satisfying outcomes.

Analogically, new software is being introduced that promises to be the AutoCAD LT version of Revit. 

Interested in testing and providing feedback for a technology preview of a lighter version of Revit?

Thought so. Go here.

Or see A Revit LT-ish Product Available for Download from Autodesk Labs.

In other words, when you pare Revit down, what’s lost in translation?

Actually, very little.

That is, unless worksharing is important to you.

Then you’re out of luck.

Have no need for photo realistic rendering?

Good – because it doesn’t support it.

Nor view filters, groups, in-Place families, massing, analysis, trusses or shared coordinates.

Nor point clouds, sun path, API, parts/assemblies, design options, adaptive components, simplified export, links, content, phasing or materials.

To reach that agile level of lightness and simplicity – and pare the program down to essentials – much of value is lost along the way.

The whole emphasis on lean practices is to reduce waste and increase value. Right?

What is lost is this:

Communicating, sharing and collaborating.

In other words, what makes BIM BIM.

The same can be said of most reductionist definitions of BIM.

The focus of a recent Linkedin BIM group challenge asked:

Is it even possible to describe BIM in TEN words or less?

Is something lost when you try to pare BIM down to its essentials?

Are 10 words enough to meaningfully describe, explain or justify BIM?

50 words, maybe.

For 24 definitions of BIM in 50 words or less look here.

14 words?

Possibly.

But restricting a working definition of BIM down to 10 words means that people only describe what is important to them.

Not to each other.

Does BIM need to be enabled by bloated software?

If by ‘bloated’ you mean that it also communicates, allows for sharing and collaboration?

Then afraid so.

Here’s a smattering of the 10-word definitions. You decide if any capture the magic of BIM.

In terms of software:

BIM

“generates and manages building data throughout the building lifecycle”

“provides coordination to the nth degree”

“is a federated data models of an asset throughout its life cycle”

“creates, develops and manages all building information digitally”

“3D + Data + Relationship”

“is an acronym for construction utopia”

“forces people to communicate throughout the building process”

 “is the digital representation of a facility’s physical and functional characteristics”*

 “is 3D coordination before construction prevents surprises in the field”

“is everything you need to know about your building, forever”

“is the bridge between design and close-out at your fingertips”

As an activity

BIM

“is building a building twice: first in 3D, then real life.”

In terms of a process

BIM

“is the process of gathering and managing building lifecycle information”

“is a process that federates information for a buildings lifecycle”

Some are contrived

BIM

“digitally builds the facility before gets built”

Some are downright tortured

BIM

“prebuild virtually with end-user mentality, incorporate product data, add value”

In terms of information

BIM

“is complete information about building and that can be repossessed anytime”

In terms of knowledge

“is structuring and relating data to maintain information and generate knowledge”

Some unnecessarily obfuscate

BIM

“is an ontology based knowledge management infrastructure for virtual construction based on standardized business process workflows”

Some define BIM in terms of what it is not:

BIM

“isn’t Software it includes people, processes, standards and methods”

“IT’s NOT SOFTWARE, it’s process, methodology and collaboration”

My favorite

I like this (albeit a compromise at 14 words)

“Regardless of the tools you use BIM requirements enforce that you collaborate with others”

But for BIM to succeed, perhaps a little compromise is in order?

* a reworded version of the definition provided by the National Institute of Building Sciences.

5 Comments

Filed under BIM, collaboration, construction industry, definition, workflow

This Week in Tweets


Here’s a smattering of the BIM and IPD-related tweets that my followers on Twitter have retweeted to their followers.

In addition to technology and collaboration, my tweets focus on creativity, architecture, design and construction.

Oh, and books, writing and poetry.

We’ll save those for another post. The following tweets are on BIM and IPD.

By browsing the list of micro-posts you will get a good idea of how I use it.

If you like what you see, please follow me on Twitter @randydeutsch

Collaborative #Learning for the Digital Age http://bit.ly/q7jsiH#SM#education

The End of the #Architecture Firm? http://lnkd.in/FR6th7#AEC#architects

Stewart Brand: “Once a new technology rolls over you, if you’re not part of the steamroller, you’re part of the road.” #BIM

Giving a talk about my #BIM book http://bit.ly/oHqJJ0 in #Chicago 9/12 at IIT Architecture | Master of Integrated Building Delivery

Lateral thinking and problem solving, perhaps. But #creativity is one lesson you ‘can’t teach’ http://bit.ly/qFUxBC

#BIM for Infrastructure http://bit.ly/o9I19I#construction#AEC#engineering

Building performance as brand http://bit.ly/qwaK1Q#performativity

Conference Addresses #Performativity of #Architectshttp://bit.ly/oMNrkQ#ACSA > SHoP Architects http://bit.ly/pOQl8v

Attend Integrated Project Delivery: A Catalyst for Collaborative #Design & #Constructionhttp://bit.ly/qdG9jl#IPD#architecture

Barriers to Successful #BIM by BIG BIM little bim author Finith Jernigan http://bit.ly/r1ctWH & http://amzn.to/ra2vTb > helpful checklist

MIT Unravels the Secrets Behind Collective Intelligence – HINT: IQ Not So Important http://www.singularityhub.com #collaboration

Enjoyed doing the panel yesterday with @newvoodou & @pwnakazawa at #SMPS2011 on “Trends: What to Look for When You Don’t Know What’s Coming”

If each GC firm wore their #BIM Score on a jersey, what would yours say? Where is your firm along the spectrum? http://bit.ly/pjP3le

 “Is Integrated Practice Taking Hold?” http://bit.ly/h7fpwL#IPD

 “People may accept or resist a technology not for what it does but for how it makes them feel.” Sherry Turkle in http://amzn.to/qML0XV

@threefourteen New in that it involves all stakeholders from earliest stages each of whom has input into what goes into making the decisions

@threefourteen Can get confusing…with integrative design, integrated buildings, integrated design process, integrated practice & IPD!

#BIM and Integrated Design: Strategies for Architectural Practice available pre-publication as an eBook http://bit.ly/pxOcxp#IPD

@Neil_BIM Great question. Due to length I had to cut the international BIM chapter but the remaining content is still applicable. Thanks.

Program Management Integrated with #BIM, demonstrating use of BIM-based PM tools via @jvandezande@HOKNetworkhttp://bit.ly/nZ31xp

Finding Your Way Around #BIMhttp://bit.ly/pqlKnb#IPD

Read Finith E. Jernigan’s book, Makers of the Environment, free http://bit.ly/rndf1q executive summary http://bit.ly/qbwA3Q

Design futures: Finith E. Jernigan’s blog, Makers of the Environment helps us look into the future http://bit.ly/reeZwM

Makers of the Environment is an information model whose foundation is a printed book. A book information model http://bit.ly/reeZwM#BIM

How seriously has recession damaged the construction industry? 65 markets suffer #construction declines of >75% http://bit.ly/rqCNMb

read the first chapter of my book free http://bit.ly/pIdOc1

#BIM & #IPD have a 8-in-10 chance of completing a project on schedule & within budget, an improvement fr previous stats http://bit.ly/pIdOc1

Let’s collaborate: AUGIWorld August 2011 #Collaboration issue is out! @AUGIhttp://bit.ly/fpjryJ http://www.augi.com/ #BIM#IPD

John Moebes, director of #construction at Crate & Barrel, will be a presenter at Integration Utah ACEO 9/20 http://bit.ly/mYO5xp#IPD

John Moebes highlights successes & challenges of #IPD. Crate & Barrel’s presentation on Integrated Project Delivery http://bit.ly/mYO5xp

Is IPD the right fit across the board? What It Means to #IPDhttp://bit.ly/nhv9qI#AEC#construction

As you start to integrate projects, remember Communication—Integration—Interoperability—Knowledge—Certainty drive #BIMhttp://amzn.to/qbFIxX

Tradition and legacy systems must not overshadow good business decisions. http://amzn.to/qbFIxX#BIM#CAD

You can only become expert in a limited range of issues. This makes #collaboration others a necessity not a luxury http://amzn.to/qbFIxX#IPD

Scripting Cultures: Architectural Design & Programming. Computer #programming integral to the digital #design process http://bit.ly/pHC30K

Mastering Autodesk Revit MEP 2012 from @WileyDesign – best tutorial & reference providing coverage of #BIM#MEPhttp://bit.ly/qBWS8i

Good discussion on whether #architecture school is the best place to learn #BIM and #IPDhttp://bit.ly/rkSZk3#AIATAP

One architect’s favorite iPad apps for #architects and #architecturehttp://bit.ly/odqWdT

@case_inc brought on board by Advanced Cast Stone to provide all LOD 400 #BIM#fabrication modeling > see the results http://bit.ly/hZmJ3y

Due to seismic shift, #BIM Migrates to Apple Platforms | Building #Design + #Constructionhttp://bit.ly/pIZoHg

eBIM™ Existing #BIM launches in UK > focuses on growing demand for accurate surveys of existing buildings http://bit.ly/o21h1i#AEC

What is #BIM about? Is it about software? Is it about technology? Is it about #Revit? > It’s about people @revit3dhttp://bit.ly/oK3Asy

Leave a comment

Filed under BIM, collaboration, construction industry, education, Integrated Design, Integrated Project Delivery, IPD

Taking BIM and IPD to Task


Making BIM Beyond Boundaries Actionable

In my recent piece in DesignIntelligence, BIM Beyond Boundaries, I argue for widening our outlook and reach as we deepen our skills.

No doubt, a somewhat unpopular stance today.

In the article I am not suggesting that designers, architects and managers abandon their expertise:

  • Project designers can always deepen their skills.
  • Project architects can always improve their technology chops and knowhow.
  • Project managers can do the same for their leadership skills.
  • And others can improve their specialties.

What I am suggesting is for you to spend the next 90 days branching out.

Looking at new ways to work and practice effectively with your teammates.

So often these thought pieces remain just that – saved in our hard drives or on our nightstands – but seldom put into use.

Here, in this post, I unpack some key points from the article BIM Beyond Boundaries.

And make some suggested next steps that you can take based on the prescriptions made in the article.

Think of it as a way of taking the article to task – by making the content actionable.

Avoiding the typical response to feel good articles by answering the question: What now?

What follows are some suggested resources, activities and links to use as action items as you build your breadth as well as depth.

Skim the bullets below, find one that captures your attention and start expanding:

  • Form an informal group. Meet to discuss ways your firm can collaborate and partner
  • Bring other professionals into the office for lunch-and-learns – not just sales reps
  • Form a mastermind group in your firm and hold each other accountable for change items

“Opting for depth over breadth of expertise is a false choice that will lead individuals, organizations, the profession, and industry in the wrong direction.”

  • Apply the concepts from Daniel Goleman’s bestseller, Emotional Intelligence, into your workplace
  • Assign chapters and meet at lunch to discuss the book
  • Start here then apply it to leadership EQ
  • Read a book on social intelligence such as Social Intelligence: The New Science of Human Relationships or Social Intelligence: The New Science of Success

“Several forces are converging to create an unprecedented and timely opportunity for organizations that have embraced building information modeling (BIM). These forces — including the rise of the expert, the growing complexity and speed of projects, and BIM’s increasing recognition as an enabler, catalyst, and facilitator of team collaboration — also present significant challenges that can be overcome with the right approach and mindset.”

  • Expertise today requires change and growth, not retention of facts. Read Carol Dweck’s Mindset: The New Psychology of Success for a thorough understanding of the difference between a fixed and growth mindset
  • Identify those within your organization with a fixed mindset and determine their likelihood of working towards one of growth
  • Aim to make all of your key personnel those with growth mindsets
  • Consider applying ideas from Building Expertise: Cognitive Methods for Training and Performance Improvement to your organization’s learning initiatives
  • Consider joining  and participating in discussions on what it means to be an expert, among others, at the KA Connect LinkedIn group.

“At one time, being an expert meant knowing more than one’s competitors in a particular field. Firms that reinforced their expert culture hoarded information, which resulted in silos of expertise. Today, many firms are looking to hire people perceived as building and software technology experts, shortsightedly addressing today’s needs at the expense of tomorrow’s.”

  • Not all positions require the applicant to be an expert. See, for example, Why I Will Never, see Ever Hire A “Social Media Expert”

“Due to the speed and complexity of projects, we do not have time to acquire knowledge the old way — slowly, over time, through traditional means.”

  • Familiarize yourself with  the concept of “wicked problems”
  • Familiarize yourself with the concept of ‘design assist’ and other ways to tackle fast, large-scaled and complex projects
  • Access answers and best practices through online discussions and social media

“Being an expert is no longer about telling people what you know so much as understanding what questions to ask, who to ask, and applying knowledge flexibly and contextually to the specific situation at hand.

“Expertise has often been associated with teaching and mentoring. Today it’s more concerned with learning than knowing: less to do with continuing education and more with practicing and engaging in continuous education.”

  • Read the important new book, A New Culture of Learning. By exploring play, innovation, and the cultivation of the imagination as cornerstones of learning, the authors create a vision of learning for the future that is achievable, scalable and one that grows along with the technology that fosters it and the people who engage with it.
  • Give copies of the book to key colleagues and meet to discuss concepts and ideas with the intention of applying them to your organization.

“Social media presents the would-be expert with both opportunities and challenges. Working with the understanding that somebody somewhere has already done what you are trying to do, design professionals, like agile technology experts, can find what they’re looking for by tapping into their networks and aggregating the responses. Conversely, due to the rise of social media, virtually all anyone has to do today to be considered a technology expert is to call themselves one. Because social networks allow people to proclaim themselves experts, it can be hard to know who to turn to, resulting in the rise of otherwise unnecessary certifications.”

  • Apply what you’ve learned via ideas from the book The New Social Learning: A Guide to Transforming Organizations Through Social Media.

“To grow one’s professional reputation, expertise in BIM counter-intuitively requires unlearning, detachment, collaboration, and developing both deep skills and broad interests.”

“We tend to cooperate conditionally, responding to the behavior of others.”

  • If you haven’t done so already, read the blog post ‘Unlearning to Collaborate’
  • Take a look at Why We Cooperate by Michael Tomasello for a better understanding of how we all start out as collaborators and unlearn these behaviors along the way  

“As we grow in our careers, we tend to focus more on people issues and less on technology.”

  • When you consider your own career, does this sound accurate? What implications might this have in terms of how you focus your attention and time in the future? What can you start doing now to prepare?

“Achieving higher levels of BIM use — including analysis, computation, and fabrication — requires skills and a mindset that allow us to work productively and effectively in a collaborative setting.”

  • Many firms that have adopted and implemented BIM software solutions have not used the technology or process to their greatest advantage. To do so not only requires familiarizing yourself with these higher uses – but working more collaboratively with others on the team.
  • If you – or your organization – have not already done so, make the commitment to take-on BIM’s higher uses in the next 6-12 months.
  • Invite local experts who have used BIM for analysis, for sustainability, for fabrication to come to your office to give a demonstration. Or better yet, request and invite and make a visit to their operations to see how they are utilizing the tools and work processes. A simple visit such as this can spark a future teaming or partnering opportunity.
  • Follow-up by discussing how you can go about implementing this higher use of BIM on your next project.

“With BIM, technical expertise should not be considered more important than increasing one’s social intelligence, empathy, or the ability to relate well with others.”

  • Re-familiarize yourself with the concept of attaining and developing T-shaped skills.
  • Consider placing primarily T-shaped people on your project teams
  • Read-up on the subject in ‘T-Shaped BIM’ as well as here.

There is so much more we can all do to become well-rounded professionals.

These suggestions are only a start.

At the risk of overwhelming you, I’ll stop for now with these.

If you know of other sources – or have other suggestions or ideas of your own – please let us know by leaving a comment.

Leave a comment

Filed under BIM, BIM expert, BIM organizations, collaboration, construction industry, design professionals, Integrated Design, Integrated Project Delivery, IPD, people, process, workflow

BIM and Integrated Design – The Week in Tweets


Again, here are the BIM and IPD-related Tweets that my followers on Twitter have shared with their followers (retweeted or RT in Twitter parlance.)

Take a look. Click on the links to find articles, websites and other resources.

If you are not a Tweeter, by browsing the list of micro-posts you will get a good idea of how I use it. And if you like what you see, follow me on Twitter @randydeutsch

Enjoy!

@fedenegro @AddThis ‘BIM Implementation Guide’ is a great book – you can read my short review (and others) here http://amzn.to/m7M16o

 

Revit Roles: summary of the basic tasks in a #Revit environment from the perspective of a project manager http://bit.ly/l3OQ8P

 

Oldie but goodie. The Freshman: levels of #knowledge required of users to be successful making content for #Revithttp://bit.ly/jYZh8g#BIM

 

School’s out? New Course to Explore #BIM Contracts & Risk Allocation http://bit.ly/jM0GDs

 

BIM: Designing tomorrow http://bit.ly/mrTPLy#BIM

 

7 key ways BIM will affect you and your work: De-coding #BIMhttp://bit.ly/kZGOrA

 

Designing for Failure in the Cloud http://onforb.es/ix0QKI

 

Proof that #construction industry is reducing costs stemming from waste & adopting open-standard #BIMhttp://bit.ly/lAvueX #AEC #IPD

 

Building owners: Construction Owners Association of America addresses #BIM & #IPD from perspective of the owner http://www.coaa.org/ #AEC

 

He will be missed: Ralph Lerner, former Princeton #architecture school dean, dies at 61 http://bit.ly/m4DIrx #architects

 

Driving #Construction Project Success thru Neutral Trust Based #Collaborationhttp: //bit.ly/baJkzA & comments http://bit.ly/l1yhhg #BIM #IPD

 

22 people have “liked” my book ‘BIM and Integrated Design’ at http://amzn.to/kCKUuP & it doesn’t even come out for 3 months!

 

Interested in Making Your Company BIM-friendly? Check out AGC’s #BIM Education Program http://bit.ly/kyVQJ2 #AEC

 

Tech Trends: On-Site iPads Change the #AEC Game http://bit.ly/knm5Ym

 

Set them straight as soon as possible: Have the #BIM Truth Talk with Your Boss @Cadalyst_Maghttp://bit.ly/mlakae

 

Visit the Knowledge Lens: Northwestern U’s Center for Learning & Organizational Change, a community of practitioners http://bit.ly/bfXiPd

 

Improving Building Industry Results thru Integrated Project Delivery & Building Information Modeling http://bit.ly/mxOlcv #BIM #IPD #AEC

 

BIM Viewing Comes to the iPad – Portable #BIM now fully implemented http://bit.ly/lHZAEi #AEC #construction #architects #revit

 

@Opening_Design Have you seen this? via @fedenegro Basecamp for architects? http://ow.ly/52X0a #mergersandaquisitions #AEC

 

Top 10 List of “What BIM is NOT…” Vote today! via @caddguru http://bit.ly/ma7Jqt

 

Blog prediction: Autodesk will launch an integrated, multidisciplinary version of its #BIM solution: #Revit Integrated http://bit.ly/kugzGt

 

Webinar provides guidance to #construction counsel for evaluating whether & when to use AIA or ConsensusDOCs for #IPD http://bit.ly/mn7wLf

 

Integrated Project Delivery Invites Innovative Insurance Model http://bit.ly/lp0DIR > ‘invites’ but doesn’t innovate or solve #IPD

 

Polymath, Renaissance person, Multidisciplinarian (!) – Why we all must become one http://zd.net/kRoKem

 

Interview w Vinnie Mirchandani author of The New Polymath: Profiles in Compound-Technology #Innovations http://zd.net/91pytu

 

#Revit – Family Standards and Best Practices Version 2.0 (Kindle Edition) for creation of Revit family files http://amzn.to/kF0tZ4 #BIM

 

Check out the Northern California Virtual Design & Construction (NCVDC) website & blog – just launched http://ncvdc.org/ #BIM #IPD

 

Reserve yr spot! 5th Annual USC Symposium on Extreme #BIM: Parametrics & Customization. Friday, July 8 small f(r)ee http://bit.ly/lBCUsL

 

N Cal Virtual Design & Construction (NCVDC) meeting May 26, 2011 5:00 PM (PT) @perkinswill_SF http://bit.ly/lVqh0E #BIM #IPD #VDC #AEC

 

What do part-time & executive MBA programs have in common with Integrated Project Delivery? They’re both alternative delivery models! #IPD

 

Manhattan Real Estate Software did a nice write-up on my blog today (take that, Altos Research!) #BIM Grows Up http://bit.ly/kIPQDN

 

Fact: Half of all presentation proposals for CoreNet Fall 2011 Summit were on Building Information Modeling #BIMhttp://bit.ly/kIPQDN

 

FYI my rss feeds https://bimandintegrateddesign.com//rss.xml http://architects2zebras.com/rss.xml http://thedesignstrategist.com/rss.xml

 

To compete in a knowledge-based economy business leaders need to reinvent themselves as innovators in services http://bit.ly/ixxU24

Leave a comment

Filed under BIM, BIM Director, BIM expert, BIM trainer, collaboration, construction industry, defining BIM, education, Integrated Design, Integrated Project Delivery, IPD, modeling, process

First Fire, then the Wheel, and now BIM


Owners didn’t ask for BIM.

Nor for IPD.

Never did.

Not then and not now.

Its part of the disconnect we’re experiencing in the profession and industry.

BIM may be purpose-built,

But nothing’s purpose-driven until it’s owner-driven.

And right now, other than healthcare and government mandates, very little is being driven by anybody.

So while owners didn’t ask for BIM or for IPD,

What they did ask for was less waste and adversity, more predictability and value.

We said we can give you that.

And we did.

Or so we thought.

Because we didn’t give them less and more of what they asked for.We gave them BIM and IPD.

To us – they’re the same.

One leads to the other.

But to them – there’s a difference.

And that difference takes the form of a gap.

A gap we’ve yet to fill.

We as a profession and industry may be making great strides in adopting, implementing and using the technology and collaborative work processes necessary to make BIM and integrated design a reality.

But we’re doing little when it comes to explaining what BIM and IPD can do – what they’re capable of – to the client.

Go on.

Take them out of the box for the owner.

Give them a demonstration of how they work.

Put in the batteries and turn them on.

BIM first.

Then, once you got that going, show them how BIM enables IPD.

In giving owners BIM and IPD, we gave them exactly what they wanted and needed.

We gave them fire.

And we gave them the wheel.

Only they don’t know that yet.

Because we haven’t told them.

And until owners know what BIM and IPD mean to their goals and to their businesses, they won’t value them.

After taking BIM and IPD for a spin, they’ll be back into the bin with the other toys.Folks,

This wheel’s on fire
Rolling down the road
Best notify my next of kin
This wheel shall explode!

Bob Dylan, who wrote these lyrics, an evocation of chaos, turns 70 this week.

If BIM and integrated design hope to see their 70th birthday

We need to do a better job of describing, explaining and justifying just what they mean.

What they do.

And who they do it for.

Design professionals and constructors are visual types.

If words were our strong suit, we’d be on the owner side ourselves.

But what is obvious to us may not be clear to them.

We need to become better storytellers – for that’s really how one learns best.

And not by berating with bullets and numbers.

The LinkedIn group, BIM for Owners, and James Salmon’s Collaborative BIM Advocates are a start.

We need to convince our owners to not only join, but join the discussion and participate.

We need them to understand how they, and their project, can benefit.

And while data and hard numbers help, in the end it’s not a rational choice.

But one of trust, gut and intuition.

Above all, we need to enchant and woo and wow our clients,

So that they in turn proactively request BIM and IPD on every job.

Until owners no longer have to ask for them.

Because BIM and integrated design will be – a foregone conclusion – part of the atmosphere.

As ever-present, prevalent – and necessary – on design and construction projects as windows and doors.

Then, and only then, we’ll have something to celebrate.

3 Comments

Filed under collaboration, construction industry, design professionals, Integrated Design, Integrated Project Delivery, IPD, process, Uncategorized

He’s just not that into you…or BIM


Today I’m going to introduce you to a new acronym.

That’s right. One more.

Just this last one, then we’re through. Done. Kaput. I promise.

You ready? Good.

JAT

There, that wasn’t so bad. Right?

It’s short for

Just a Tool

As in…

Well, you know.

The oft heard sentiment that

“BIM is just a tool”

Here, it’s the word “just” – not “tool” – that triggers my outrage.

And this rant.

So, fasten your seatbelts.

Not “just.”

BIM is not “just” anything.

This blog’s brand is more horse feathers than high horse, more horse sense than nonsense – so accept what I’m about to say as an exception to the rule.

My anger – and incredulousness (yes, it’s a word) – in online discussions and interviews.

The nonchalance of those who declare that

“That’s not a BIM problem.”

As in

“I have a hospital to design in a seismic zone and I have no time to do it. That’s not a BIM problem.”

Or

“That’s not an issue brought about by BIM.”

That BIM is “just a tool” – like it’s just a can opener or a pair of pliers or a hammer.

If you only have a hammer, you tend to see every problem as a nail.

–          Abraham Maslow

“If we didn’t have it – we’d use something else.”

As in

“No Revit? No problem. I’ll use a stapler.”

At least until BIM becomes a staple in the industry.

These dismissives come from those who are immersed in the technology

Like fish who, it is said, cannot discover water – or like Madge in the 70’s Palmolive ads

You’re soaking in it

They swat away the insinuation that what they are using or doing is anything more than a revved-up 2H pencil with an off-handed dismissive sweep of the hand like they were swatting flies.

But a tool?!

The way that the iPhone is just a tool.

Or the GPS is just a tool.

Or the human brain…

Only that BIM is ALL of these in one.

And the add-ons are BIM’s apps.

App-like tools available for every part of the BIM process.

BIM is not a tool, authoring, analyzing or otherwise.

Apps are tools, I’ll concede you that.

BIM is…

BIM is a process

BIM is our saving grace

BIM is our ticket to ride

BIM is our pass out of here

BIM is our card that says pass GO

BIM is our last golden ticket

BIM is our salvation

BIM is the innards of an intricate clock

BIM is the white horse you rode in on

BIM is the deus ex machina – that arrives at the end of the play to save everything

BIM, the enabler

BIM, the balm

BIM makes IPD possible

And also likely, relevant, necessary and inevitable.

BIM is more than what’s happening on your desktop.

No one would say

BIM is just a process.

BIM is just a strategy.

BIM is not just a technology: software is.

BIM is a disruptive technology. And…

BIM requires that you just focus less on Revit, ArchiCAD and their add-ons and more on process and strategy

BIM is a product

BIM is an IT-enabled, open standards based deliverable and collaborative process

BIM is a facility life-cycle management requirement

BIM is a fundamentally different way of creating, using, and sharing building lifecycle data

BIM is just evolving and will continue to as the capabilities of user and technology improve

BIM can serve as a reliable basis for decision making

BIM is a rebirth of excitement and hope. (T/Y Alberto Palomino, master of the poetry and metaphysics of BIM)

No one asks “Can peanut butter exist without jelly?”

Yes, BIM can exist without IPD as IPD can work without BIM

Just as peanut butter can exist without jelly.

But

WHY ON EARTH WOULD ANYONE WANT TO DO THAT?!

And yes,

BIM is a pretty amazing, evolved, in-process of developing, still in-progress

Tool.

But a pretty amazing one at that. And…

Get on your high horses, people – the Age of Aquarius for design professionals is upon us.

Just as HAL – the fictional computer in Space Odyssey – plus one letter in the alphabet is IBM (H<I, A<B, L<M) so too CAD minus one letter is BIM*

*Except for the last two letters. Shucks.

Definitions of Just BIM

No one would ever say

BIM? It’s just a computable representation of the physical and functional characteristics of a facility.

or

BIM is just information use, reuse, and exchange just with integrated 3D-2D model-based technology. No big deal.

or

BIM is just a single repository including both graphical and non-graphical documents – that’s all.

or even

BIM is just a building design and documentation methodology characterized by the creation and use of coordinated, internally consistent computable information about a building project in design and construction. Nothing more, really.

Why qualify it?

So fuggedaboutit.

There’s no need for the acronym JAT.

BIM isn’t “just” any thing.

So stop saying it.

BIM just is.

10 Comments

Filed under BIM, defining BIM, process, workflow

27 Reasons to read Mastering Autodesk Revit Architecture 2011 now, before it comes out


What are you doing on August 2, 2010?

That’s the day* Mastering Autodesk Revit Architecture 2011 – or MARA2011 for short – written by the authorial triumvirate of Eddy Krygiel, Phil Read and the inestimable James Vandezande comes out.

I may not know where I’ll be on August 2nd – but I can tell you this.

On August 1st I’ll be waiting in line at the Winnetka Book Coop awaiting the 12 midnight book release.

Winnetka – with its trophy kids and designer dogs – hasn’t seen anything like this since the last Harry Potter book launch.

There’s been not a little online and offline buzz about the meaning and significance of the launch date.

August 2, 2010 is a Monday. Except in leap years, no other month starts on the same day of the week as August. That’s significant.

Also, the book is being released while the Sturgis Motorcycle Rally is being held. That’s too bad for the bikers but gives everyone else an edge.

No Book, No Review, No Business

But if the book hasn’t been released yet – how can I reliably review the book without having read it?

The same way that the book’s authors are giving book signings without the book.

For more on this see Book signing – without the book!

It is apparently possible to not only sign books that haven’t  been published but also to talk about books you haven’t read – a practice encouraged in places of higher learning and France.

The French masterpiece How to Talk About Books You Haven’t Read is considered a work of inspired nonsense that answers the question:

What are we supposed to do in these awkward months before books are released in which we’re inclined to talk about a book we haven’t read?

In other words:

How to talk about How to Talk About Books You Haven’t Read if you haven’t in fact read it?

You want to know how I am able to share with you the contents of Mastering Autodesk Revit Architecture 2011 before its publication date?

It’s one helluva story. Here goes.

You may or may not recall that an entire truckload of copies of the new Mastering Autodesk Revit Architecture 2011 book, both weighing and costing an estimated one million pounds, had been stolen just months before the eagerly awaited BIM book was due to appear in bookstores.

The good news is that all of the yet-to-be-sold books have been recovered unscathed – with the sole exception of one copy that had not been accounted for until it became apparent that the “invaluable” (attorneys) prototype was left in a Silicon Valley bar by a disgruntled, as yet unidentified 2D CAD manager and later purchased for an undisclosed sum ($37.78) by Bimodo.com who proceeded to take the book apart page by page to study its substantial innards, dissecting it and posting embarrassing pictures and revealing video detailing its impressive features.

I’d link to the videos but I have to consider this blog’s family-oriented audience.

The authors, who closely guard details about their unreleased books, were too busy disclosing the most minute details of their top-secret book in their blogs to be reached for comment.

As chance would have it I happened to be writing this very post at an adjacent table to the 2D CAD manager in the Silicon Valley bar prior to his call to Bimodo.com –

a call incidentally, shamelessly and stupidly made on the non-functioning prototype of the next generation iPhone that had also been inadvertently left in the same bar

– and was able to observe the following information about the book while he proceeded to make the dastardly, ill-advised call to Bimodo.com on a wall-hung pay phone.

For those who would like to appear knowledgeable about Mastering Autodesk Revit Architecture 2011 prior to its well-anticipated release, read on.

Mastering Autodesk Revit Architecture 2011 Factoids

Due to state laws forbidding the transfer of smuggled books over state lines I can only share with you a small sampling of what’s in store.

This much we know to be true:

The book runs 976 pages**

Each author wrote the equivalent of a 325 page book (Eddy no doubt one-upped with a 326th page)

The book is written in English, unless you are unfamiliar with Revit.

27 Reasons to read the book now, before it comes out

REASON 1: Reading the book now, before it comes out, will give you a competitive advantage over your competition.

When your competition returns in September they won’t know what hit them.

REASON 2: Aug 2 is a good book launch date.

Your competition is on the beach relaxing, sipping margaritas while you’re sailing by on your inflatable-of-choice reading away.

So clear your calendar. Leave August – the hottest month of the year – wide open.

You may want to keep in mind that August is the month therapists are on vacation. I’m only saying.

REASON 3: The authors – likened elsewhere to Ruth, DiMaggio and Mantle (Yankees) and Luciano Pavarotti, Plácido Domingo and José Carreras (Mets) – held nothing back and pulled no punches – in the scribing of their tome.

On August 2nd, you will hold in your hands everything these guys know. Period.

Having given their all, the authors themselves have been reduced to empty shells, mere husks of their former selves. You’re now the keepers of their content – they’re barely haircuts in suits. Enjoy.

REASON 4: For the same reason you work in BIM and Integrated Design – without everything all perfectly worked out.

For the same reason you work in BIM without the assurances of complete interoperability.

For the same reason you work in Integrated Design without signing a right of reliance (you don’t?!)

You find coping mechanisms and plug-ins.

Patches and workarounds.

Patience, faith, hope and confidence that everything will be worked out in time.

Besides, design professionals for a living envision what is not there.

It is one of our core attributes and competencies.

That is what we do.

We don’t need a book to read it any more than we need a building to design it.

Don’t let the pesky detail that the book does not yet exist stand in your way of reading it.

REASON 5: Get a jump start, before the book comes out, and form a study group. In advance – upon return from summer vacation each employee prepares to present a different topic at a lunchtime lunch and learn. Each employee picks a chapter and runs with it. Does the double duty of providing much-needed presentation experience for emerging employees. Until the release date – you can do some prep work – some of the heavy lifting – prepare a work plan, a study plan, look online here at the table of contents to decide where you will focus first. Or read on.

27 Even Better Reasons + 3 Bonus Reasons

Here are all the reasons you need to read this outstanding as yet-to-be-published book – the best book I haven’t read in ages.

Here are all 27 of them from the book’s table of contents

Part I: Fundamentals provides discussions of key BIM and Revit concepts before giving readers a hands-on look at the Revit interface.

1 Beyond Basic Documentation.

2 The Principles of Revit: Tools and UI.

3 The Basics of the Revit Toolbox.

Part II: The Revit Workflow, explores today’s Revit workflows and introduces readers to templates, worksharing, and managing Revit projects.

4 Configuring Templates and Standards.

5 Managing a Revit Project.

6 Understanding Worksharing.

7 Working with Consultants.

8 Interoperability: Working Multiplatform.

Part III: Modeling and Massing for Design dives into modeling and massing and offers detailed information on the crucial Family Editor as well as visualization techniques for various industries.

9 Advanced Modeling and Massing.

10 Conceptual Design and Sustainability.

11 Phasing, Groups, and Design Options.

12 Visualization.

Part IV: Extended Modeling Techniques covers documentation, including annotation and detailing, and explains how to work with complex walls, roofs and floors as well as curtain walls and advanced stair and railings.

13 Walls and Curtain Walls.

14 Roofs and Floors.

15 Family Editor.

16 Stairs and Railings.

Part V: Documentation.

17 Detailing Your Design.

18 Documenting Your Design.

19 Annotating Your Design.

20 Presenting Your Design.

Part VI: Construction and Beyond, the final portion of the book, discusses Revit for contractors and facility managers, working with Revit in the classroom (high school through graduate), virtualization, working with the API, fabrication for film and stage, and advanced, time-saving tips and tricks

21 Revit in Construction.

22 Revit in the Classroom.

23 Revit and Virtualization.

24 Under the Hood.

25 Direct to Fabrication.

26 Revit for Film and Stage.

27 Revit in the Cloud.

There you have it. 27 great reasons to read Mastering Autodesk Revit Architecture 2011 now, before it comes out.

Want three more reasons to make it an even 30? Here are 3 more bonus reasons:

28 Mastering Autodesk Revit Architecture 2011’s focused discussions, detailed exercises, and compelling real-world examples are organized by how users learn and implement Revit, an approach that will resonate with Revit users of all skill levels.

29 The expert authors developed this practical reference and tutorial based on years of experience using the program and training others to do so.

30 Unlike the competition, Mastering Revit Architecture is organized by real-world workflows and features detailed explanations, interesting real-world examples, and practical tutorials to help readers understand Revit and BIM concepts so that they can quickly start accomplishing vital Revit tasks.

DON’T WAIT

For the same reason that many professionals should avoid waiting until things are perfect and all worked-out with their technology before jumping-in, there is no better time than now – before the book is published and distributed – to read this insightful guide.

The release date will come sooner than you think – the future is nearer than you think – so act now.

Click here and free yourself.

If you are an instructor, you may request an evaluation copy for this title.

In the meantime, come August 2 – you will have the immaculate door-stopper and show stopper.

Follow the book on Facebook by checking the book out on the Mastering Autodesk Revit Architecture 2011 Facebook page

And while at it, follow them on Twitter http://twitter.com/masteringrevit

Don’t wait. BIM operators are standing by.

* Important Update: Now you really can read Mastering Autodesk Revit Architecture 2011 before it comes out! I just learned from a very reliable source (the publisher) that this post identified the official announced publication date (when they pop the champagne) as August 2 – which remains accurate – but in fact failed to mention that you can get Mastering Autodesk Revit Architecture 2011 from the Wiley website as early as July 12, and from Amazon very shortly thereafter and at most stores where books are sold by July 26. See comment below for more on this. Do not drink and read.

** The final official tally is 1080 pages – the equivalent of each author having written a 360 page book!

16 Comments

Filed under BIM, education, Integrated Design, Integrated Project Delivery, IPD, modeling, workflow